The detour is in effect, and remember commercial vehicles should not be using the Park Loop Road detour! There have been instances when vehicles have been pulled over for not following the rules. It is so important to drive carefully and slowly on the detour route. Please follow the directions of the flaggers and try to move over to give the construction crews as much room as possible.

Photo Maine DOT
Photo Maine DOT
loading...

Here's the anticipated work plan. Remember everything is weather dependent.

The contractor will be working in the areas stated below for the week:

  • Continuing work on a large drainage pipe at the West Street/Eden Street intersection
  • Continuing new drainage work from Days Inn to the College of the Atlantic
  • Working on new waterline from West Street to Highbrook Road
  • Working on sidewalks from Crooked Road to the entrance of Acadia National Park