The crews from R.F. Jordan and Sons are back at it, early Monday, September 22nd, working on the Southwest Harbor Construction Project. They provided the following plan for the week

RFJordan will be continue work along Main Street this week, between Herrick Road and Seal Cove Road,  performing the following work:

  • Installing water services
  • Installing sewer services
  • Installing new storm drain

R.F. Jordan requests your patience and understanding while driving through the construction project. Please be sure to slow down, and follow instructions of the flaggers to insure the safety of the workers and to help minimize delays, as they work on this important infrastructure update for the Town of Southwest Harbor.