Bar Harbor Rt 3 Construction Work Plan Week Ending April 27
Here is the latest construction work plan for the week ending April 27th for the Bar Harbor Route 3 Construction Project. The scheduling is weather dependent, so with the expected rain, work could be delayed
Traffic will be 2 way until paving begins, which is scheduled tentatively to begin during the first few weeks of May. After that, the 1 way detour will be up and running again utilizing the Park Loop Road.
This week's scheduled work include
- Working on curbing at the Acadia National Park entrance, around Sand Point Road and various repair areas along the project
- Working on widening the shoulder area at the end of the Sand Point Road
- Placing slotted drains at the Colony in Hulls Cove
- Working on improving drainage at Duck Brook
- Working on repairing a water main leak in front of the Park Entrance on Thursday, April 25th.
More From WDEA Ellsworth Maine






![Conversation with MDI Hospital’s Chrissi Maguire – March 7 [VIDEO]](http://townsquare.media/site/496/files/2025/03/attachment-Popper-Maguire.jpg?w=980&q=75)

![MDI High School Placed on Brief Lockdown Friday Afternoon [UPDATED]](http://townsquare.media/site/496/files/2025/02/attachment-mdi-high-school.jpg?w=980&q=75)