Bar Harbor Road Construction This Week
Here's the latest work schedule for the Bar Harbor Area road construction as issued by the Maine Department of Transportation for the week ending April 8th. All work is weather dependent and subject to change
The contractor will continue placing a water line from Sand Point Road towards Old Bar Harbor Road.
The utility companies will continue conducting telephone pole work from the Acadia Park Entrance to Duck Brook, from Sand Point Road to Barton's Lane and from West Street towards the Eagle Lake Road. This work will entail setting new poles and running wires. Some work will also be done on the traffic signals at the intersection of the Eagle Lake Road and Route 3.
The contractor will being placing new underdrains from Baymeath Road towards Sand Point Road.