It is a short week for the contractors working on the Bar Harbor Route 3 Construction Project, as work resumed on Tuesday, May 28th after the Memorial Day Holiday. Here is the work plan for the week ending June 1st.

The 1 Way Detour using the Park Loop Road is in effect, and will remain in effect until further notice.

Here's where the contractors will be working through Saturday, June 1st.

  • Placing loam from the Bluffs to Highbrook Road South
  • Placing ADA detectables from Duck Brook to Highbrook Road North
  • Preparing for paving the roadway at various locations along the project
  • Paving surface from the Crooked Road to the entrance of Acadia National Park
  • Landscaping from the College of the Atlantic to the Eagle Lake Road