The crews at R.F. Jordan and Sons Construction are making great progress on the Beechland Road construction project in Ellsworth.

Plans for Friday, September 5th and next week include grading for the placement of the balance of the binder course pavement. The plans are to pave the end of next week, weather permitting.

R.F. Jordan and Sons thanks the traveling public for their patience during this infrastructure improvement project. Please continue to follow the instructions of the flaggers and please drive slowly in the construction zone. Have a great weekend.