R.F. Jordan and Sons Construction plan on working as follows in Southwest Harbor this week

R F Jordan will be adding a new valve to the existing temporary water main at Herrick Road on Main Street starting at 10AM on Wednesday, June 18th.

This work will require service interruptions for 6 to 8 hours for water department customers in the following areas:

  • Main Street, from Herrick Road to the gas station

 

R F Jordan will be connecting the existing water main on Forest Avenue to the new water main on Main Street starting at 10AM on Wednesday, June 18th.

This work will require service interruptions for 6 to 8 hours for water department customers in the following area:

  • Forest Avenue

 

R F Jordan will be performing the following work during the week:

  • Milling the existing roadway between Wesley Avenue and Herrick Road on Monday, June 16th
  • Milling and Patching trenches along Main Street between Wesley Avenue and Herrick Road, starting on Tuesday, June 17thh
  • Installing Curbing and Sidewalks along Main Street between Wesley Avenue and Village Green Way, starting on Tuesday, June 17th
  • Paving sidewalks along Main Street between Wesley Avenue and Village Green Way near the end of the week, weather-permitting

 

Again, we thank you for your cooperation and patience as work progresses on this project.