Crews from R.F. Jordan and Sons Construction are back at work in Southwest Harbor on Monday, September 29th, and have provided the following construction plan for this week

 

R F Jordan will be performing the following work during the week of September 29th:

  • Installing new Sewer and Water service connections between the Herrick Road and the Gas Station
  • Installing new Storm Drain between Herrick Road and the Gas Station
  • Constructing new sidewalk on the East side of Main Street, on either side of the Seal Cove Road intersection

R.F. Jordan thanks the traveling public for their patience and understanding during this project. Please continue to drive slowly in the construction zone and to follow the directions of the flaggers, as they attempt to keep delays to a minimum.